20F: Decker Main WWPS Pump Replacement – Phase 2

Consultant: Bowen Collins & Associates, Inc.

Contractor: To be determined

Status: The District met with the Consultant to review 90% plans and specs on February 5, 2020. The District would like to complete the construction of this project in 2020 and had previously considered pre-purchasing the pumps to avoid delays. However, because the project design is currently ahead of schedule, this allows the District to advertise the bid documents as early as February 17, 2020 and still meet the project schedule without pre-purchasing pumps.