Project Status Updates

In an effort to ensure long lasting infrastructure and high quality culinary water and sanitary wastewater services, GHID is continually updating aging pipes and facilities and addressing problematic areas within these crucial systems. Our goal is to keep the Water and Wastewater systems in good repair in order to avoid costly emergency repairs when pipes break or collapse. It is our goal to carry out these projects and improvements with minimal disruption to our customers. Take note of our upcoming projects and feel free to contact our staff at 801.968.3551 with any concerns. Please be patient with us while we work to provide you with the high level of service you have come to expect from GHID.

Updated December 2019

18B: 4100 South Waterline Replacement - Bangerter Highway to 5600 West

Consultant (Design): Horrocks Engineers (WVC/UDOT - Local Governments Project)

Consultant (CM): PEC (Project Engineering Consultants)

Contractor: Geneva Rock Products, Inc.

Status: The Contractor is beginning to install the loops on the 16/20-inch transmission line in preparation for storm drain laterals to be installed. This work will take place in the middle of the road over the winter.

18C: Meter 80 Piping & Breeze Chemical Feed Project

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Burlington Civil, Inc. (Declared Bankruptcy)

Contractor: Corrio Construction, Inc. (Completion Contractor)

Status: The District is close to finalizing the Tender Agreement with Great American Insurance Company and Corrio Construction, Inc. to complete the rest of the work. To allow safe and effective snow removal, Corrio has agreed to go ahead and install a temporary T-patch and remove the steel plates on 6400 West prior to executing the Agreement. Due to current commitments on other projects, Corrio plans to commence work in January 2020.

18F: Hillsdale WWPS Decommissioning & Gravity Sewer

Consultant: CRS Engineers

Contractor: Lance Excavating, Inc.

Status: Construction is ongoing and the sewer installation is close to completion. Asphalt paving on public right-of-way is complete. The Contractor plans to demolish the existing lift station building and work on the landscaping by the end of December 2019.

18G: MVC Waterline Betterments

Consultant: Parsons Transportation Group, Inc. and CRS Engineers

Contractor: Mountain View Corridor Constructors (A Kiewitt-Clyde Joint Venture)

Status: Betterments within the 3500 South right-of-way are underway and are scheduled to be complete by the end of the year.

18H: Pioneer WWPS Replacement Project - Site Selection

Consultant: Bowen, Collins & Associates, Inc. (Engineering)

Consultant: Mulvey Enterprises (Real Estate Agent)

Contractor: To be determined

Status: A preliminary design report has been completed. District staff will begin preparing a Request for Proposals for the design of the project.

18K: Printers Row Waterline Replacement Project

Consultant: Stanley Consultants

Contractor: Rolfe Excavating & Construction, Inc

Status: The District and Consultant have received and reviewed submittals from the Contractor. The first progress meeting was scheduled for December 4, 2019, and the Contractor plans to work along 1800 West Street in December and keep working while the weather is favorable.

19C: 2200 West Waterline Project

Consultant: Franson Civil Engineers

Contractor: To be determined

Status: The Consultant is working on review comments from the District. When that is complete, the plans and specifications will be sent to the Utah Division of Drinking Water for review prior to bidding.

19D: PRV Upgrades & Large Meter Replacements

Consultant: Forsgren Associates, Inc.

Contractor: To be determined

Status: The design will be completed by the end of the year.

19F: 3600 West Waterline Project

Consultant: PSOMAS

Contractor: To be determined

Status: The Consultant submitted 60-percent design drawings to the District on November 21, 2019. Copies of the draft drawings have been transmitted to Taylorsville-Bennion Improvement District and Taylorsville City for their review and input. Design work is ongoing.

19G: Well No 8 Chlorinator Replacement

Consultant: GHID.

Contractor: Corrio Construction, Inc. (PSI system)

Status: District staff prepared a Request for Proposals (RFP) to solicit vendors to upgrade the chlorination equipment at Well No. 8. The RFP allowed District staff to select the ‘best value’ system and to utilize existing equipment (such as storage tanks and pumps) as much as possible. The system is undersized for current chlorine demands.

20A: Redwood Road - 4100 South to 3100 South Water and Sewer Upgrades Project

Pre-design: Horrocks Engineers

Consultant: To be determined

Contractor: To be determined

Status: The waterlines along Redwood Road from 4100 South to 3100 South have reached the end of their useful life. In addition, the District’s current sewer collection system along Redwood Road has almost reached capacity and will not be able to support new developments planned along the corridor. This project will replace and upgrade the waterlines along Redwood and add additional sewer capacity to support future development. The waterline portion is funded by the Utah Division of Drinking Water SRF Loan.

20B: Rushton Groundwater Treatment Plant

Consultant: To be determined

Contractor: To be determined

Status: Confluence Engineers and J-U-B have substantially completed their reports for treating the District’s groundwater to remove iron, manganese, and ammonia. If all the recommendations are implemented, customer complaints regarding water quality will be significantly reduced. One of the first steps is to construct filters to remove the iron and manganese. The first project will be constructing a facility at Well No. 12 to treat Well No. 12, No. 1 and No. 17. This project is funded by the Utah Division of Drinking Water SRF Loan.

20C: 2020 Sewer Rehabilitation Project

Consultant: GHID

Contractor: To be determined

Status: The recurring Cured-In-Place Pipe (CIPP) Lining project was designed in-house and issued for bidding on November 27, 2019. Bid documents are available for viewing and download on the State of Utah Procurement website and a link to this website is included in the District’s procurement webpage. Bids are due on December 23, 2019.

20D: Kent Booster Station Replacement and Tank Purchase Project

Consultant: GHID

Contractor: To be determined

Status: This project will purchase the 2 surplus 5 MG tanks from Jordan Valley Water Conservancy District, replace the existing pump station, and make other various energy and piping improvements.

District staff released a Request for Proposals on December 4, 2019. Proposals are due January 15, 2020 with an award expected at the February Board meeting.


Capital Project Map

*Click on a colored section to view more information about a project.