Project Status Updates

In an effort to ensure long lasting infrastructure and high quality culinary water and sanitary wastewater services, GHID is continually updating aging pipes and facilities and addressing problematic areas within these crucial systems. Our goal is to keep the Water and Wastewater systems in good repair in order to avoid costly emergency repairs when pipes break or collapse. It is our goal to carry out these projects and improvements with minimal disruption to our customers. Take note of our upcoming projects and feel free to contact our staff at 801.968.3551 with any concerns. Please be patient with us while we work to provide you with the high level of service you have come to expect from GHID.

Updated April 2019

17F: Tank Farm Master Plan

Consultant: Hansen, Allen & Luce

Contractor: To be determined

Status: The consultant is wrapping up their recommendations and will prepare a written report.

18B: 4100 South Waterline Replacement - Bangerter Highway to 5600 West

Consultant: Horrocks Engineers (WVC/UDOT - Local Governments Project)

Contractor: To be determined

Status: Bids were received by UDOT on March 19, 2019. The bids are significantly higher than the construction cost estimate.

18C: Meter 80 Piping & Breeze Chemical Feed Project

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Burlington Civil, Inc.

Status: Construction is ongoing.

18D: Wells No. 12 & 14 Chemical Treatment

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Petersen Brothers Drilling

Status: Construction work at Well 12 is ongoing.

18F: Hillsdale WWPS Decommissioning & Gravity Sewer

Consultant: CRS Engineers

Contractor: To be determined

Status: The contractor has been issued a Notice to Proceed document with a project state date of May 13, 2019. The Substantial Completion is November 4, 2019.

18G: MVC Waterline Betterments

Consultant: UDOT Design-Build Contractor

Contractor: UDOT Design-Build Contractor

Status: The District continues to meet with UDOT’s Design-Build Contractor (CRS Engineers). Final designs for the Masters Drive waterline, the Masters Drive to 5725 West sewer and the Darle Avenue Waterline were submitted on March 28, 2019.

18H: Pioneer WWPS Replacement Project - Site Selection

Consultant: Bowen, Collins & Associates, Inc. (Engineering)

Consultant: Mulvey Enterprises (Real Estate Agent)

Contractor: To be determined

Status: The closing for the property purchase was held on March 15, 2019. A deed will be delivered when it has been recorded. A preliminary design report will be completed in the near future.

18I: Well No. 12 Landscaping Project

Consultant: Project Engineering Consultants

Contractor: To be determined

Status: The consultant has completed the final design for the site. We will hold off on construction until the water quality study is complete and sites are selected, which may affect the design of this site.

18J: GHID Headquarters Landscaping

Consultant: J-U-B Engineers

Contractor: To be determined

Status: A 90-percent design meeting was held on April 2, 2019. We anticipate advertising for bids in late May.

18K: Printers Row Waterline Replacement Project

Consultant: Stanley Consultants

Contractor: To be determined

Status: The design is ongoing but almost complete. The consultant is working on the NEPA compliance documents. The next milestone is the contractor prequalification advertisement. The District will accept prequalification information from contractors interested in bidding the project. Bids will only be accepted from those contractors that are prequalified by the District and no other contractors will be eligible to bid.

18L: Well No. 16 Generator Replacement

Consultant: Bowen, Collins & Associates, Inc.

Contractor: Nelson Brothers Construction Company

Status: Construction will resume when the generator is delivered in late May.

19A: Sewer Rehabilitation Project

Consultant: None - GHID Design

Contractor: Planned and Engineered Construction, Inc.

Status: The construction contract is in place. Material submittals have been provided. Field work will not start until the summer of 2019.

19B: Manhole Rehabilitation Project

Consultant: None - GHID Design

Contractor: To be determined

Status: Numerous manholes on 3100 South are located downstream of forcemain discharge locations. These manholes have experienced significant corrosion due to high concentrations of hydrogen sulfide in the forcemain discharge stream. This project will rehabilitate 16 manholes by lining the interior with polymer concrete inserts.

The construction contract is in place. The Contractor has made field measurements of the manholes so the inserts can be fabricated. Work will not start until the summer of 2019.


Capital Project Map

*Click on a colored section to view more information about a project.