Project Status Updates

In an effort to ensure long lasting infrastructure and high quality culinary water and sanitary wastewater services, GHID is continually updating aging pipes and facilities and addressing problematic areas within these crucial systems. Our goal is to keep the Water and Wastewater systems in good repair in order to avoid costly emergency repairs when pipes break or collapse. It is our goal to carry out these projects and improvements with minimal disruption to our customers. Take note of our upcoming projects and feel free to contact our staff at 801.968.3551 with any concerns. Please be patient with us while we work to provide you with the high level of service you have come to expect from GHID.

Updated May 2019

17F: Tank Farm Master Plan

Consultant: Hansen, Allen & Luce

Contractor: To be determined

Status: The consultant has completed a written report and District staff are reviewing their recommendations.

18B: 4100 South Waterline Replacement - Bangerter Highway to 5600 West

Consultant: Horrocks Engineers (WVC/UDOT - Local Governments Project)

Contractor: Geneva Rock Products, Inc.

Status: The pre-construction meeting was held May 9, 2019.

West Valley City has contracted with Horrocks Engineers for Public Involvement Services during construction. They will be the main point of contact for residents and businesses along 4100 South during construction, as well as provide information to residents and work with the contractor to solve problems.

West Valley City has also created a CCT (Community Coordination Team) Incentive for the contractor (facilitated by Jacques and Associates). This incentivizes the contractor to work with residents and businesses to quickly solve issues that arise during construction. The members of the team then vote on how much the contractor receives of the incentive ($80,000 total).

18C: Meter 80 Piping & Breeze Chemical Feed Project

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Burlington Civil, Inc.

Status: Construction is ongoing. The contractor is currently behind schedule and is working to rectify this issue. It is anticipated that the work will be completed by the end of May.

18D: Wells No. 12 & 14 Chemical Treatment

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Petersen Brothers Drilling

Status: Construction work at Well No. 12 is ongoing. Some of the well development operations completed so far include well cleaning with surging and pumping, placement of treatment chemicals in the well to soak, agitation and removal of chemicals, well bailing, and well video logs.

18F: Hillsdale WWPS Decommissioning & Gravity Sewer

Consultant: CRS Engineers

Contractor: To be determined

Status: A preconstruction meeting is scheduled for May 14, 2019.

18G: MVC Waterline Betterments

Consultant: UDOT Design-Build Contractor

Contractor: UDOT Design-Build Contractor

Status: The District continues to meet with UDOT’s Design-Build Contractor (CRS Engineers). A preconstruction meeting was held on April 25, 2019 for the construction of the Masters Drive waterline betterment and 3705 South sewer relocation. Construction of the Masters Drive waterline started on May 6, 2019.

18H: Pioneer WWPS Replacement Project - Site Selection

Consultant: Bowen, Collins & Associates, Inc. (Engineering)

Consultant: Mulvey Enterprises (Real Estate Agent)

Contractor: To be determined

Status: A preliminary design report will be completed in the near future.

18I: Well No. 12 Landscaping Project

Consultant: Project Engineering Consultants

Contractor: To be determined

Status: The consultant has completed the final design for the site. We will hold off on construction until the water quality study is complete and sites are selected, which may affect the design of this site.

18J: GHID Headquarters Landscaping

Consultant: J-U-B Engineers

Contractor: To be determined

Status: A 90-percent design meeting was held on April 2, 2019. We anticipate advertising for bids in late May. The consultant is finalizing the design for the monument signs.

18K: Printers Row Waterline Replacement Project

Consultant: Stanley Consultants

Contractor: To be determined

Status: The design is ongoing.

18L: Well No. 16 Generator Replacement

Consultant: Bowen, Collins & Associates, Inc.

Contractor: Nelson Brothers Construction Company

Status: The generator will be delivered on May 10, 2019. The custom base mounted fuel tank and access platform will be delivered on July 3, 2019. The fuel tank was custom built to fit on the existing concrete platform. The generator will be stored at the contractor’s yard until the tank and platform are delivered. Construction will resume in July.

19A: Sewer Rehabilitation Project

Consultant: None - GHID Design

Contractor: Planned and Engineered Construction, Inc.

Status: The construction contract is in place. Material submittals have been provided. Field work will not start until the summer of 2019.

19B: Manhole Rehabilitation Project

Consultant: None - GHID Design

Contractor: To be determined

Status: Numerous manholes on 3100 South are located downstream of forcemain discharge locations. These manholes have experienced significant corrosion due to high concentrations of hydrogen sulfide in the forcemain discharge stream. This project will rehabilitate 16 manholes by lining the interior with polymer concrete inserts.

The construction contract is in place. The Contractor has made field measurements of the manholes so the inserts can be fabricated. Work will not start until the summer of 2019.

19C: 2200 West Waterline Project

Consultant: Franson Civil Engineers

Contractor: To be determined

Status: The District met with the consultant to review the 60-percent design drawings on April 25, 2019. Design is ongoing.


Capital Project Map

*Click on a colored section to view more information about a project.