Project Status Updates

In an effort to ensure long lasting infrastructure and high quality culinary water and sanitary wastewater services, GHID is continually updating aging pipes and facilities and addressing problematic areas within these crucial systems. Our goal is to keep the Water and Wastewater systems in good repair in order to avoid costly emergency repairs when pipes break or collapse. It is our goal to carry out these projects and improvements with minimal disruption to our customers. Take note of our upcoming projects and feel free to contact our staff at 801.968.3551 with any concerns. Please be patient with us while we work to provide you with the high level of service you have come to expect from GHID.

Updated December 2018

16G: GHID Headquarters Parking Lot & Landscaping Renovations

Consultant: J-U-B Engineers

Contractor: Peckham Asphalt Paving

Status: The work is substantially complete. The Contractor is working on punch list items.

17E: PRV Upgrades & Large Meter Replacements Project

Consultant: Forsgren Associates, Inc.

Contractor: Corrio Construction, Inc.

Status: The work is approximately 90-percent complete.

17F: Tank Farm Master Plan

Consultant: Hansen, Allen & Luce

Contractor: To be determined

Status: This project is currently on hold, awaiting final Utah State Division of Drinking Water guidance on storage requirements. District staff are in the process of calculating storage requirements for submittal.

17G: Building A Reconstruction

Consultant: Design West Architects

Contractor: Broderick and Henderson Construction

Status: The project is substantially complete. The Contractor is working on completing the punch list, including the drive-up window and window lettering.

18B: 4100 South Waterline Replacement - Bangerter Highway to 5600 West

Consultant: Horrocks Engineers (WVC/UDOT - Local Governments Project)

Contractor: To be determined

Status: The District’s Betterment Agreement with UDOT to fund the waterline construction is in place. Some third party utility work will start the first of the month.

18C: Meter 80 Piping & Breeze Chemical Feed Project

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Burlington Civil, Inc.

Status: Construction activities have not started. In the meantime, the District and Consultant are responding to Submittals and Requests for Information submitted by the Contractor.

18D: Wells No. 12 & 14 Chemical Treatment

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Petersen Brothers Drilling

Status: The project was advertised for bid on November 14, 2018 and a mandatory pre-bid conference/site visit was held on November 20th. The Bid Opening was held on December 3, 2018.

18F: Hillsdale WWPS Decommissioning & Gravity Sewer

Consultant: CRS Engineers

Contractor: To be determined

Status: Design work is ongoing.

18G: MVC Waterline Betterments

Consultant: UDOT Design-Build Contractor

Contractor: UDOT Design-Build Contractor

Status: UDOT issued a Notice to Proceed the week of December 3, 2018. Work will start in early 2019.

18H: Pioneer WWPS Replacement Project - Site Selection

Consultant: Bowen, Collins & Associates, Inc. (Engineering)

Consultant: Mulvey Enterprises (Real Estate Agent)

Contractor: To be determined

Status: The District and Mulvey Enterprises continues to pursue prospective property parcels on which to site a new replacement WWPS.

18I: Well No. 12 Landscaping Project

Consultant: Project Engineering Consultants

Contractor: To be determined

Status: The consultant has completed the conceptual design for the site and District staff are reviewing. We will hold off on construction until the water quality study is complete, and sites are selected.

18J: GHID Headquarters Landscaping

Consultant: J-U-B Engineers

Contractor: To be determined

Status: Design work is ongoing.

18K: Printers Row Waterline Replacement Project

Consultant: Stanley Consultants

Contractor: To be determined

Status: Design work is ongoing.

18L: Well No. 16 Generator Replacement

Consultant: Bowen, Collins & Associates, Inc.

Contractor: To be determined

Status: The project was advertised for bid on November 14, 2018 and a non-mandatory pre-bid meeting/site visit was held on November 19th. The Bid Opening was held on November 29, 2018.


Capital Project Map

*Click on a colored section to view more information about a project.