Project Status Updates

In an effort to ensure long lasting infrastructure and high quality culinary water and sanitary wastewater services, GHID is continually updating aging pipes and facilities and addressing problematic areas within these crucial systems. Our goal is to keep the Water and Wastewater systems in good repair in order to avoid costly emergency repairs when pipes break or collapse. It is our goal to carry out these projects and improvements with minimal disruption to our customers. Take note of our upcoming projects and feel free to contact our staff at 801.968.3551 with any concerns. Please be patient with us while we work to provide you with the high level of service you have come to expect from GHID.

Updated June 2019

17F: Tank Farm Master Plan

Consultant: Hansen, Allen & Luce

Contractor: N/A

Status: The consultant has completed a written report and District staff are reviewing their recommendations and calculating potential cost/benefit savings.

18B: 4100 South Waterline Replacement - Bangerter Highway to 5600 West

Consultant: Horrocks Engineers (WVC/UDOT - Local Governments Project)

Contractor: Geneva Rock Products, Inc.

Status: The pre-construction meeting was held May 9, 2019.

The pre-construction meeting was held May 9, 2019. Work started on May 28, 2019. The initial construction phase will install new storm drain piping at the center of the right-of-way. The contractor is also installing loops on existing District pipelines.

18C: Meter 80 Piping & Breeze Chemical Feed Project

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Burlington Civil, Inc.

Status: Construction is ongoing. The contractor is currently behind schedule and is working to rectify this issue. It is anticipated that the work will be completed by the end of July 2019.

18D: Wells No. 12 & 14 Chemical Treatment

Consultant: Hansen, Allen & Luce, Inc.

Contractor: Widdison Turbine Service (Well 12); Petersen Brothers Drilling (Well 14)

Status: Construction work at Well No. 12 is on hold until the new pump and motor gets delivered to the site. Chemical feed tubes will be added to the well to allow future chemical treatments to be done in-house.

18F: Hillsdale WWPS Decommissioning & Gravity Sewer

Consultant: CRS Engineers

Contractor: Lance Excavating, Inc.

Status: A Notice to Proceed was issued with a start date of May 13, 2019. A preconstruction meeting was held the following day. The work is scheduled to start the end of June or the first week of July.

18G: MVC Waterline Betterments

Consultant: Parsons Transportation Group, Inc. and CRS Engineers

Contractor: Mountain View Corridor Constructors (A Kiewitt-Clyde Joint Venture)

Status: The District continues to meet with UDOT’s Design-Build Contractor (CRS Engineers). The Masters Drive waterline installation is complete. Other betterments will start in the near future.

18H: Pioneer WWPS Replacement Project - Site Selection

Consultant: Bowen, Collins & Associates, Inc. (Engineering)

Consultant: Mulvey Enterprises (Real Estate Agent)

Contractor: To be determined

Status: A preliminary design report will be completed in the near future.

18I: Well No. 12 Landscaping Project

Consultant: Project Engineering Consultants

Contractor: To be determined

Status: The consultant has completed the final design for the site. We will hold off on construction until the water quality study is complete and sites are selected, which may affect the design of this site.

18J: GHID Headquarters Landscaping

Consultant: J-U-B Engineers

Contractor: Nelson Brothers Construction Company

Status: Bidding documents were distributed to prospective bibbers in May and a pre-bid conference was held on June 5, 2019. The Bid Opening was held on June 17, 2019 and the only bid received was submitted. The bid amount exceeded the engineering estimate. The contractor is amenable to the modification of the monument signs to bring the bid amount closer to the engineering estimate.

18K: Printers Row Waterline Replacement Project

Consultant: Stanley Consultants

Contractor: To be determined

Status: A notice inviting contractors to prequalify to bid on the 18K: Printers Row Waterline Project was distributed on June 6, 2019. Prequalification Proposals are due on June 25, 2019. The District will evaluate the proposals and only those contractors that are prequalified will be invited to bid on this project.

18L: Well No. 16 Generator Replacement

Consultant: Bowen, Collins & Associates, Inc.

Contractor: Nelson Brothers Construction Company

Status: The generator will be delivered on May 10, 2019. The custom base mounted fuel tank and access platform will be delivered on July 3, 2019. The fuel tank was custom built to fit on the existing concrete platform. The generator will be stored at the contractor’s yard until the tank and platform are delivered. Construction will resume in July.

19A: Sewer Rehabilitation Project

Consultant: None - GHID Design

Contractor: Planned and Engineered Construction, Inc.

Status: The construction contract is in place. Material submittals have been provided. Field work will not start until the summer of 2019.

19B: Manhole Rehabilitation Project

Consultant: None - GHID Design

Contractor: Cody Ekker Construction, Inc.

Status: A preconstruction meeting was held on May 14, 2019. Construction started the following day. The work is approximately 60-percent complete.

19C: 2200 West Waterline Project

Consultant: Franson Civil Engineers

Contractor: To be determined

Status: The District met with the consultant to review the 60-percent design drawings on April 25, 2019. Design is ongoing.

19D: PRV Upgrades & Large Meter Replacements

Consultant: Forsgren Associates, Inc.

Contractor: To be determined

Status: In 2009, the District initiated a program of upgrades to existing pressure reducing valve (PRV) stations. The annual upgrade projects included evaluations of the structural, piping and valves, and electrical systems of the existing PRV stations and preparation of design work for miscellaneous upgrades.

The 2016 and 2017 projects were expanded to include upgrades and/or replacements of large customer water meter vaults. The 2019 project includes design of 20 customer water meter vault replacements.